The two ways a water right dies
A conditional right has to be defended every six years. An absolute one can be lost by not using it. Both leave a paper trail.
Water rights on a listing are usually described as though they were title: you have them or you do not. Two mechanisms in Colorado law make that wrong, and both run on the court record rather than on the deed.
Conditional rights and diligence
A conditional right is a place in line held for a project that has not yet diverted water. It is real, it is decreed, and it keeps its date. It also has to be defended: the owner must return to the water court on a schedule and show that work is still being done toward putting the water to use.
The owner of a conditional water right must file an application for a finding of reasonable diligence every six years, and a failure to file operates as an abandonment of the conditional right.
C.R.S. 37-92-301(4)
A conditional right holds a place in line for a project that has not yet diverted water. It has to be defended in court every six years, and the record shows what happens when it is not.
DWR water rights transactions, Colorado water courts · computed September 2026
The consequence of missing the filing is not a warning or a fine. The right ends, and with it the date that made it worth anything. Several hundred rights in the state carry a record of exactly that having happened. For any conditional right on a listing there are therefore two questions with hard answers in the record: when was diligence last found, and when is the next application due.
structures
Structures whose record carries at least one diligence filing, by how long ago the last one was. Six years is the statutory interval, so anything past it is a question rather than a verdict: the filing may exist and not yet be in the record we can read.
Colorado water court resumes and DWR transactions · computed September 2026
And this is where a report has to be careful about what it is looking at. A last diligence finding more than six years old is NOT proof the right is dead. It may mean the application was filed and the resume naming it has not been parsed into the record we read; it may mean the right went absolute and left the diligence cycle entirely. So the Rights report gives the deadline and the case number, and names the water court as the decider. It does not declare a right dead.
Absolute rights and non-use
An absolute right is not on a clock, but it can be abandoned by a sustained intent not to use it, and long non-use is the evidence that intent is inferred from. The division engineer publishes a decennial abandonment list naming structures proposed for abandonment; an owner who does not object within the statutory window is bound by the result.
A structure appearing on that list is not a verdict, and plenty of owners protest and win. It is, however, a document that exists, that a buyer should read, and that a seller has no obligation to mention.
Reading the resumes
Everything filed in a Colorado water court appears in a monthly resume: the application, the case number, the structure, and a legal description of where the water is taken. They are published as prose, they are not consistent between divisions or across decades, and they are the only place some of this is written down.
That prose is where a lot of the work is. A resume may write a section list as "Sec. 14, 15 & 22", or glue the marker to the number, or abbreviate the township in four different ways in one paragraph. Parsing it loosely under-reads real filings; parsing it strictly attaches a filing to the wrong ground. The parser here was rebuilt against the corpus rather than against a specification, and its recall is tested case by case, because a filing missed is a filing the report says does not exist.
Which questions answer this
- Rights report, "Could I lose it, and by when?": when diligence was last found, when the next filing is due, and whether the right has been on an abandonment list.
- Rights report, "Is anyone filing nearby who could hurt me, and what’s my objection deadline?": open water court applications naming the section, with the last day to object.
- Rights report, dates not to miss: each diligence, abandonment and objection deadline on one list.
Each item gives the case number it came from, so a reader can tell a record that shows nothing from a record that was not read.
This is general information about Colorado law and records. It is not legal advice or a title search. What applies to a particular parcel is settled by the documents filed against it.